Payment milestone questions to ask before accepting a quote
“Deposit and balance” does not tell the buyer what must happen before each payment. Ask the supplier to propose amounts, due dates, payee, and evidence for every milestone. The commercial terms must then be reviewed for the specific transaction.
Define the release event
A deposit might follow purchase-order acceptance; a later payment might follow approved samples, an inspection result, or shipping documents. State which records are required and who checks them. If a sample is rejected, clarify whether the next payment waits for a corrected sample or other remedy.
Check identities and changes
Compare the payee with the contracting and invoicing parties. Agree on an independent confirmation channel for changed bank instructions. A new email alone should not amend the approved payee. Keep the final schedule attached to the purchase order; do not rely on an early sales message once the quantity, scope, or delivery arrangement has changed.
Worked payment schedule
After creating a 500-unit request in the RFQ builder, ask the bidder to complete a milestone table: 30% at acknowledged purchase order, 70% after the agreed inspection report, or its actual proposed terms. Name the document and payee for each stage. If the sample fails, ask whether the balance remains paused while it is corrected. Common error: comparing the total price but overlooking that the lower bidder asks for full payment before production evidence exists.
Source context: U.S. International Trade Administration — Perform Due Diligence supports this limited point: The ITA recommends checking prospective business partners and continuing due diligence. The buyer procedure above is Suppliers Help editorial guidance. Source checked 2026-09-27.